Volume Date Feakes Lock Sheering Lock Sawbridgeworth Lock Tednambury Lock Spellbrook Lock Twyford Lock South Mill Lock Head of Navigation
                   
RAIL 845/41 18.9.1914   Mill purchased            
RAIL 845/42 18.8.1915                
RAIL 845/43 8.9.1916 Inspected Reconstruction about to be commenced            
RAIL 845/44 28.7.1917 Inspected Rebuilding recently completed Inspected Inspected        
RAIL 845/45 20.7.1918 Inspected   Inspected              
RAIL 845/46 19.7.1919 Inspected   Inspected   In course of reconstruction          
RAIL 845/47 1.10.1920 Inspected   Inspected   Inspected   Just been reconstructed About to commence rebuilding      
RAIL 845/48 3.9.1921 Inspected   Inspected   Inspected   Inspected   Just been reconstructed      
RAIL 845/49 17.6.1922 Inspected  Inspected  Inspected  Inspected  Inspected Reconstruction about to be commenced    
RAIL 845/107 9.10.1923 Inspected Inspected Inspected Inspected Inspected Inspected Just been reconstructed  
RAIL 845/108 4.7.1924 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Declared reopened
RAIL 845/109 23.7.1925 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/110 17.7.1926 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/111 15.7.1927 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/112 6.7.1928 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/113 5.7.1929 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/114 4.7.1930 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/115 3.7.1931 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/116 1.7.1932 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/117 8.7.1933 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/118 7.7.1934 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/119 6.7.1935 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/120 4.7.1936 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/121 3.7.1937 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/122 2.7.1938 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/123 24.6.1939 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
                   
RAIL 845/127 23.6.1945 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/127 6.7.1946 Inspected Inspected Inspected Inspected Inspected Inspected Inspected Inspected
RAIL 845/128 12.7.1947 Inspected Inspected Inspected          
 